Water Project Update
Week of September 19:
Horace Proper Schedule Update_20220919



Upcoming Work Announcement:
 
The Contractor for the Water Replacement Project is planning to begin some of the remaining work along CR 17 and Main St in Horace.
 
• The work consists of the horizontal directional drilling of the watermain along the east side of CR 17 and Main St from 8th Ave S to Center Ave and Water Service line installation.
 
• Work to complete the directional drilling of the service lines will include several access pits in the east parking lane of CR 17.
 
• 2-3 weeks is anticipated to complete the work.

 
Potential impacts to Public:
 
• Traffic Control for the parking lane closure is scheduled to be installed on the morning of Wednesday, September 21, 2022. The travelling public should drive with caution.


Note to Residents:
 
• The Contractor is responsible for providing access to all residents and business establishments whenever possible.
 
• Where temporary water is required, the Contractor will be notifying residents at least 48 hours prior to the interruption of service.
 
Please contact City Hall or the Contractor for questions/concerns.
 
Attached is a location map showing the work area.
 
Contractor:
Joshua Smith, KPH Inc.
218-329-3079
 